Datacenters and energy: why 100 GW of requests are not 100 GW of projects
Connection requests to Terna have passed 100 GW, but estimates point to 1.5-2 GW of real demand by 2030. What sets a…
Catania, Italy · Working across Italy
Technologies
The infrastructure of data: site, permits, grid and energy, tackled together.
Overview
Requesting one costs little compared with the value it can take on, which is why the queue includes concrete initiatives alongside mere grid reservations.
A datacenter consumes continuously, while solar and wind produce according to the conditions of the moment. It therefore makes sense to tackle site development and energy supply together, from the first assessments.

The numbers
Requests
Connection requests to Terna in 2026, up from about 30 GW at the end of 2024.
Estimate
Actual new load by around 2030, according to Terna's recurring estimate.
Geography
Lombardy's share alone on 31 July 2026, while much of the renewable potential is in the South and on the islands.
A solid project
Actual availability, compatible zoning, access and fibre.
A clear permitting route, with environmental assessments already set up.
Capacity justified by a user or a marketing plan, with realistic growth phases.
Technology choices consistent with the site's climate and water availability.
A connection solution compatible with the project schedule.
Long-term contracts, different technologies and, where it makes sense, storage.
How we step in
Coordination of site, schedule, costs and suppliers.
Further reading
Connection requests to Terna have passed 100 GW, but estimates point to 1.5-2 GW of real demand by 2030. What sets a…
The second MACSE auction awards 16 GWh for 2029 delivery. But the contract is only part of the assessment: connection, site and permits decide…
Legislative Decree 190/2024 reorganised permits into three regimes. How to tell which applies to a plant and what to check before filing…
Tell us where you stand: we'll tell you at which phase we can help.