Storage and MACSE: what to check before developing a BESS
The second MACSE auction awards 16 GWh for 2029 delivery. But the contract is only part of the assessment: connection, site and permits decide…
Catania, Italy · Working across Italy
Technologies
Grid-scale batteries move renewable output towards the hours when it is needed.
Overview
With the growth of solar and wind, the issue has shifted to the moment when energy is needed. MACSE, the mechanism run by Terna, is the tool the electricity system uses to contract storage over the long term.
But the contract is only part of the assessment: a BESS is judged first on connection, site and permits, then on price.

The questions
Is the connection quote valid? What works does it require, on what schedule, and is there capacity at the node?
Land availability, access, distances from homes and businesses, noise, fire prevention.
Which permit is needed, what constraints apply to the area, how it stays consistent with existing plants.
Stand-alone or paired with a solar or wind plant: sharing the connection changes costs and rules.
Do the warranties cover the contract obligations? When do the cells need replacing, and at whose expense?
If the bid isn't awarded, does the project have other credible revenue sources?
MACSE
Quotas and parameters must always be rechecked against the latest Terna and ARERA documents.
2025
10 GWh awarded, with bids over four times demand. Price at almost €13,000/MWh/year against a maximum of €37,000.
2026
Set for 24 November: 16 GWh with delivery in 2029 and a maximum premium of €27,000/MWh/year.
Prudence
A price far below the cap points to strong competition: it is wise to build the plan on prudent assumptions.
How we step in
Coordination of site, schedule, costs and suppliers.
Further reading
The second MACSE auction awards 16 GWh for 2029 delivery. But the contract is only part of the assessment: connection, site and permits decide…
Connection requests to Terna have passed 100 GW, but estimates point to 1.5-2 GW of real demand by 2030. What sets a…
Legislative Decree 190/2024 reorganised permits into three regimes. How to tell which applies to a plant and what to check before filing…
Tell us where you stand: we'll tell you at which phase we can help.